Latest ·

Steam blowing box / WHRB pressure parts for steel plant

We are proud to announce dispatch of a steam blowing box for a steel plant. Steam at 17 kg/cm² is used at the slag granulation system — a more efficient way to utilise low-pressure steam and move toward a more efficient plant system.

Alongside steel-plant steam auxiliaries, Grandeh also fabricates waste heat recovery boiler (WHRB) pressure parts that turn process exhaust heat into plant steam without dedicated fuel firing.

Scope highlights

  • Steam blowing box for slag-granulation steam service
  • Pressure parts for industrial waste-heat steam generation
  • Materials and design aligned to high-temperature / steel-plant duty
  • Ready for site erection and integration with existing headers

Enquire about similar WHRB systems for DRI, cement, furnace or turbine exhaust.

Two duties on one plant

The steam blowing box puts steam at 17 kg/cm² into slag granulation. That is low-pressure steam used where the process can take it, instead of letting the steam down further or wasting it. Separately, WHRB pressure parts recover heat from the plant’s exhaust and raise steam without a fuel fire dedicated to that stream. Both were fabricated for steel-plant temperature and for erection onto headers already on site.

The wider steel duty — furnace and DRI exhaust, gas-side materials, and the duct dampers that sit on the same plants — is on the steel plant page.

Figures that size the next one

  • Exhaust flow and inlet temperature, if the scope is waste-heat steam
  • Steam pressure at the user, as with the 17 kg/cm² granulation supply
  • Header sizes and whether the parts must match an existing boiler
GRANDEH steam blowing box for steel plant slag granulation